Comments on the Project Proposal regarding the Bujagali Hydropower Project Submitted by the AES Corporation to Senter Internationaal
1. Introduction

Bujagali Falls
International Rivers Network supports local
communities and NGOs around the world working to protect their rivers and
watersheds. It has been asked by Ugandan NGOs, including the National
Association of Professional Environmentalists, to raise the serious
social, environmental, economic and corruption–related problems of the
Bujagali hydropower project on the Victoria Nile with international
financial institutions.
International Rivers has invited Ugandan NGO representatives to
Washington DC so they could present their concerns to World Bank Executive
Directors. Several International Rivers representatives have visited Uganda, and the
project area, and International Rivers has taken up a series of issues concerning Bujagali
with AES, the World Bank and other financial institutions directly.
The Bujagali project has serious social and
environmental impacts. The power generated by it will likely not be
affordable for Uganda’s consumers, and the dam risks turning into a white
elephant project, thereby adding further to Uganda’s unsustainable debt
burden. The project will directly contravene the mandate of the CDM to
assist developing countries achieve sustainable development. Fundamental
project documents have so far been withheld from the public, and important
issues, including alleged cases of corruption, remain unresolved. No
further funding for the project should be approved while these issues
remain outstanding.
In terms of CDM validation requirements, Bujagali is a
business–as–usual project, and there is no realistic baseline scenario in
Uganda which would make emission reductions by Bujagali appear additional.
International Rivers believes that validating the Bujagali project as a potential CDM
project, or accepting it as a source of carbon credits, would cast serious
doubt on the concept that carbon trading can reduce greenhouse gas
emissions and promote sustainable development and clean energy.
2. General comments
2.1. Social impacts:
A group of NGO representatives, including from
International Rivers and Uganda’s National Association of
Professional Environmentalists, visited the Bujagali resettlement site on
July 14, 2002. They found that the resettlers were extremely unhappy about
the conditions at the resettlement site. The resettlers felt that the
quality and the size of their land plots, the access to water, firewood,
markets and social services, and the conditions of housing for the
majority of them were much inferior to the conditions at their original
homes. In a letter dated July 29, 2002, the NGOs asked AES Nile Power Ltd.
to address these problems. AESNP has so far not responded to this letter.
(The NGO letter is annexed.)
In July 2001, Ugandan NGOs submitted a complaint to the
World Bank’s Inspection Panel claiming that the Bujagali project violated
Bank policies. The Panel submitted its report to the Board of Directors in
June 2002. The Panel found that the planning for resettlement, compensation, and
the development of dam–affected communities under the Bujagali project
fell short of the World Bank’s requirements in several key areas. Problem
areas include the compensation of affected people, the Community
Development Action Plan, and the Resettlement Action Plan.
The Panel found that the Community Development Action
Plan (CDAP) is under–funded, short–sighted, and generally lacking in
detail. Its report says the CDAP "is weak and sketchy in the extreme; it
focuses almost entirely on short–term exercises; its targets are poorly
laid out; and it makes no significant or systematic effort at achieving
long–term poverty alleviation" (para. 273). The Panel report states that
as a result of the inadequacies of the CDAP, Bujagali is not in
compliance with IDA’s policy on Involuntary Resettlement.
2.2. Environmental impacts:
The Bujagali dam would be located on the main stem of
the Victoria Nile, only 8 km downstream of the Owen Falls and Owen Falls
Extension dams. The cumulative impacts of this dam cascade have never been
seriously assessed. The dam would also destroy a landscape of great scenic
beauty, with a deeply rooted cultural value and a growing importance for
Uganda’s tourism industry (see below).
The Bank’s Inspection Panel reported that there is no
Sectoral Environmental Impact Assessment (SEA) for the Bujagali project.
As the Panel stated, this is in violation of the Bank’s Operational Policy
4.01. The Panel suggests that "to be consistent with IDA policies", such a
report may still need to be undertaken (para. 136).
In June 2002, the World Bank Board of Directors approved
the Management Response to the Inspection Panel report. This Response
proposes to carry out an SEA later, as part of the Nile Equatorial Lakes
Subsidiary Action Program, which "would address future regional power
options". In violation of World Bank policies and the Panel’s
recommendations, the Bank has not assessed, and does not intend to assess,
the cumulative environmental impacts of the Owen Falls, Owen Falls
Extension, and Bujagali dams.
2.3. Economic impacts:
In several submissions to the World Bank and AES, International Rivers
demonstrated that the economic analysis of the Bujagali project was
seriously flawed, and that the economic viability of the project is
questionable. The World Bank appraisal documents contain major
discrepancies and inconsistencies, including on the projected growth of
power demand, and on the amount of investment needed in transmission and
distribution to connect Bujagali with consumers. The documents neglect
important risks, including the potential impact of climate change on the
Nile’s hydrology, and the Bank’s projections have already proven to be
over–optimistic regarding Uganda’s macroeconomic development, and the pace
of privatization in the country’s power sector.
Since economic growth and the expansion of power
connections in Uganda will likely not reach the highly optimistic
projections of the World Bank, there is a high risk that the electricity
produced by Bujagali will become unaffordable for the country’s consumers.
A devaluation of Uganda’s currency or a reduction in the Nile’s water flow
would compound the negative economic impacts of the project. (The economic
problems of Bujagali are elaborated in the report "Pervasive Appraisal
Optimism", published by International Rivers in May 2002.
The report of the Inspection Panel also raised crucial
issues regarding the economic and financial viability of Bujagali. They
include the projections for power demand and how they will be affected by
tariff increases, and the relation between system losses and the lagging
privatization process. The report disclosed that in important aspects, the
Power Purchase Agreement (PPA) is unfavorable to Uganda’s government, and
not up to "international best practice". Bujagali would make power tariffs
increase to 14 cents per kWh if it were not for debt relief measures. A
mild annual depreciation of Uganda’s currency of 10% would render the
tariffs "surely unaffordable", as the Panel puts it (para. 194).
The Panel revealed that in its zeal to promote Bujagali,
the Bank management simply dropped an important policy condition regarding
privatization when it became clear that Uganda could not comply with it.
As a result, privatization of power distribution is being delayed, and the
large amounts of private investment needed to connect Bujagali with
electricity consumers may not materialize.
The Panel report suggested, or implied, a series of
measures which needed to be taken to adequately assess the project risk
for Uganda (and the Bank Group) before it is too late. These measures
include, among others:
- an analysis of the impacts of currency depreciation
on the power tariffs (para. 184 and 214);
- an analysis of the impacts which a wider range of
demand forecasts would have on key features of the project (para. 213);
- an analysis of the risk which a delayed or
under–performing privatization has on the development of the power
distribution system (para. 215);
- adding a provision to the PPA to renegotiate the
contract for commercial reasons (para. 199); and
- adding a provision to the PPA to treat low demand as
a category of force majeure (para. 200).
It would be an effort in futility to carry out analyses
on the economics of the project after it has been approved. And the
necessary changes to the Power Purchase Agreement cannot be effected once
the project has been approved. In its Response to the Panel report, the
World Bank Management only commits to "closely monitor[ing] electricity
demand growth, billing and collection management, and tariff levels", so
that "measures can be taken appropriate to circumstances". This is not
sufficient to redress the serious shortcomings in the economic analysis of
Bujagali which the Inspection Panel identified.
Due to the economic risks, a series of financial
institutions declined to become involved in the Bujagali project. They
include Germany’s DEG, Great Britain’s ECGD, and US OPIC.
2.4. Lack of transparency and consultation
Civil society organizations in Uganda and
internationally have for many years called for public access to essential
project documents. Ugandan NGOs have requested public access to the Power
Purchase Agreement and the Economic Review of Bujagali. International Rivers has asked for
the release of the load forecast studies, i.e. the power demand
projections on which Bujagali is based. These documents are essential for
Ugandan and international civil society to judge the overall impacts of
the project.
The World Bank, AES and Uganda’s government have all
refused to make these documents publicly available. AES has not even
responded to International Rivers’s inquiries.
The Inspection Panel found that by refusing to release
the Economic Review, the World Bank violated its Policy on Disclosure of
Operational Information. The Panel further argued that the release of the
PPA, while not mandatory under World Bank policies, would be "vital if the
intent is to place the public in a position to analyze, under’stand, and
participate in informed discussion about viability of the Project and its
impact on the economy and well–being of Ugandans" (para. 91). In spite of
these findings, the documents are still being withheld from the public.
AESNP has had hundreds of meetings with affected villagers and NGO
representatives. Without access to basic project documents, such meetings
do not constitute a meaningful form of consultation.
As a result, the Bujagali project is not in compliance
with 37 (b) of the CDM, which states that as a condition of validation,
Price Waterhouse Coopers must confirm that:
" Comments by local stakeholders have been invited, a
summary of the comments received has been provided, and a report to the
designated operational entity on how due account was taken of any
comments has been received."
Given that key documents needed to assess this project
have been withheld, and that the World Bank’s own Inspection Panel has
found that this prevents stakeholders from being able to "analyze,
under’stand, and participate in informed discussion about viability of the
Project", it is clear that this crucial requirements has not been met, and
Price Waterhouse Coopers consequently should deny validation to this
project.
2.5. Allegations of corruption
Since its inception, the Bujagali project has been
marred by a lack of transparency, and by allegations of corruption. The
project was awarded to AES without any competitive bidding, but under
substantial pressure from the US embassy in Kampala. The EPC Consortium
for the project was also created without full competitive bidding.
Since 1999, newspapers and members of parliament in
Uganda have accused decision–makers, including former Energy Minister
Richard Kaijuka, to have accepted bribes from proponents of the Bujagali
project. According to The Monitor, one of Uganda’s two mainstream
English–language newspapers, Bujagali is "a complex web of deceit,
manipulation, collusion and corruption" (The Monitor, June 23,
2002).
In July 2002, Veidekke, a member of the Bujagali EPC
consortium, admitted to having extended a bribe of $10,000 to a Ugandan
decision–maker in the context of another project. Richard Kaijuka, now an
Alternate Executive Director of the World Bank, admitted to having
accepted an amount of $10,000, but denied that this was a bribe. The case
is presently being investigated by the World Bank, and by authorities in
Uganda, Great Britain, Norway, and the United States. In the meantime, the
project has been put on hold by the World Bank. The AES proposal to Senter
Internationaal fails to mention this.
3. Lack of additionality
3.1. A "business as usual" project
According to the Modalities and procedures for a clean
development mechanism as defined in Article 12 of the Kyoto Protocol, "a
CDM project activity is additional if anthropogenic emissions of
greenhouse gases by sources are reduced below those that would have
occurred in the absence of the registered CDM project activity" (Decision
17/CP.7, paragraph 43). Essentially this means that a project is
additional only if the emission reductions achieved by the project will
not occur if it is not registered as a CDM project. Otherwise, the
granting of carbon credits under the Kyoto Protocol would not result in an
actual reduction of emissions in addition to what would have occurred
anyway.
AES, in its Project Proposal, makes the following
statement in this respect:
"Management board of The AES Corporation approved
continued disbursement of their equity investment of USD 108 million in
the project. However, AES noted their expected return on investment of
14 percent is far less than what private investors require from a
project in Uganda. AES, in approving initial equity disbursement, has
requested supplementary funding (including the sale of carbon credits)
to bring their equity return up to acceptable levels."
In spite of this claim by AES, carbon credits will not
have any impact on whether or not Bujagali will go ahead. A hydroelectric
power project at the Bujagali site was first suggested by Acres
International in 1991. AES and the Government of Uganda signed a
Memorandum of Understanding to develop the Bujagali project in 1994, long
before the Kyoto Protocol was established. Since then, AES and the
Government have also signed an Implementation Agreement and a Power
Purchase Agreement in which they committed themselves to developing the
project.
Since December 2001, IDA, IFC and a number of export
credit agencies have approved funding for Bujagali. A MIGA guarantee is
still pending. On May 22, 2002, MIGA’s Management submitted a Report of
the President to the Board of Directors on the proposed guarantee. This
document summarizes the recent financial problems of AES, and then states: "AES has informed all members of the World Bank Group that it remains
committed to the Bujagali Hydropower project, in which it has already
invested more than $40 million." (Paragraph 10)
In the Project Proposal, AES claims it expects a return
on investment of 14% from the Bujagali project. According to the World
Bank’s Project Appraisal Document (Annex 5), AES Nile Power Ltd. projects
an average profit after tax of $42.2 million p.a. for the period, 2005
through 2018. With an equity investment of $115 million (at the time of
the Project Appraisal Document), these projections suggest a return that
is certainly higher than 14%. Approving carbon credits for Bujagali would
not reduce the cost of power produced by Bujagali for Uganda’s consumers,
but would simply further increase AESNP’s return on investment.
3.2. The baseline according to AES’ project proposal
As mentioned above, the granting of carbon credits must
result in investments by which "emissions of greenhouse gases () are
reduced below those that would have occurred in the absence of the
registered CDM project".
AES, in the project proposal to Senter/CERUPT, presents
a counterfactual baseline scenario to Bujagali. In a rather confusing
manner, the proposal defines the criteria for selecting the baseline
scenario as follows:
"The criteria for selecting the counterfactual are
that the planning sequence should not depend on speculative projects,
the projects included should not pose the same kind of analytic issues
as the candidate project, and subject to those constraints should be
least–cost (without Bujagali) and, of course, should be least–cost."
(sic, p. 29)
Presumably based on these criteria, AES presents a
counterfactual scenario which includes open–cycle and combined–cycle
combustion turbines with a total capacity of 300 MW for the period,
2005–2009, and is otherwise almost identical with the Bujagali scenario
(see Table 1, p. 29). In either case, AES assumes that a bagasse plant is
built by 2005. In other words, AES claims that Bujagali, if not built,
will be replaced by a series of thermal power plants. As will be
elaborated, this claim is completely spurious.
3.3. The baseline according to IFC
When preparing the Bujagali project, AES and IFC
commissioned Acres International to assess the different options for the
expansion of power generation in Uganda. The respective study has not been
released to the public, but has been summarized in an IFC document (IFC,
Bujagali Project, Summary of Economic Due Diligence, October 12, 2001,
www.ifc.org
).
This document indicates the
following net–present value costs for "non–Bujagali options" (see Table
4.1., p. 18):
- Geothermal $510.0 million
- Kalagala hydro & thermal $558.1 million
- Kalagala hydro & Karuma hydro $562.0 million
- Mini/medium hydro & Muzizi hydro $577.4 million
- Karuma hydro & thermal $600.0 million
- Kakira bagasse & large thermal $619.1 million
- Mini/medium hydro $632.3 million
- Large thermal $651.0 million
This list indicates the present value of options
according to the Acres International model of the Victoria Nile’s
hydrology. According to this hydrological model, the proposed Bujagali
project has a net present value cost of $499.3 million. A cost of $19.6
million for the foregone value–added of whitewater rafting at the Bujagali
Falls must be added to this cost. Under the hydrological assumptions of
the United Kingdom’s Institute of Hydrology, the geothermal and hydropower
options are even more favorable compared with the thermal options (see
also Table 4.1., p. 29).
By presenting the Kakira bagasse & large thermal option
as the counterfactual scenario, AES stipulates a baseline scenario to
Senter/CERUPT which ranks only as the sixth option in the non–Bujagali
baseline scenario that Acres International prepared for AES and IFC.
Presumably, the reason for this choice is that AES excluded projects that "pose the same kind of analytic issues as the candidate project", i.e.
other hydropower projects, from its project proposal. There is no evident
reason for doing so, except if the purpose is to inflate claims for carbon
credits. Price Waterhouse Coopers must insist on a more rigorous
justification for this baseline to avoid the clear impression that it was
chosen solely on the basis of being the baseline that would provide the
maximum possible credits.
3.4. The potential of geothermal energy in Uganda
Uganda is generally acknowledged to have a geothermal
potential of about 450 MW. Preliminary geological and geochemical
investigations of three promising fields have been conducted, but so far,
no site drillings have been carried out. The African Development Bank
recently approved a project to assess alternative energy resources in
Uganda, which will include pre–feasibility studies of promising geothermal
sites.
The options assessment carried out by Acres
International for IFC and AES demonstrates that if the economic value of
rafting at the Bujagali Falls is included (which is foregone if Bujagali
is built), geothermal energy is the least–cost option for the expansion of
power generation in Uganda, and cheaper than Bujagali. The Economic Review
of Bujagali estimates the cost for geothermal power to be $2,000/kW. The
World Bank’s website on geothermal indicates this cost to be
$1,150–2200/kW (www.worldbank.org).
In comparison, the cost of Bujagali, with a budget of $582 million and a
capacity of 200 MW, will amount to $2,910/kW.
AES project proposal argues that "the geothermal
resource in Uganda remains speculative" (p. 27), and that according to the
Economic Review of Bujagali, the earliest that geothermal might be
available in commercial quantity is 2010.
International experience, including in a World Bank
project in Kenya, shows that geological sites are usually explored in two
to three years, and that geothermal power plants typically take another
two to three years to be built. The Inspection Panel in its report found
that the estimate for the construction time of geothermal plants used in
the Bujagali Economic Review was "pessimistic" (para. 238). At this point
in time, geothermal power plants in Uganda are no more speculative than
the Bujagali project.
AES’ attempt to claim undeserved carbon credits results
in a baseline scenario which in Uganda’s power sector is unrealistic both
on economic and political terms. In economic terms, it would make most
sense for Uganda to rapidly explore the geothermal sites which have been
identified as having a promising potential, and to develop respective
geothermal power plants. This option is being pursued by the Government of
Kenya, which intends to increase the share of geothermal power in the
country’s overall power supply from 5% to 37% by 2015.
Even if geothermal energy appears to be more economic,
large, centralized hydropower projects offer bigger political,
bureaucratic and financial spoils than alternative energy sources. So if
corruption or the social and environmental concerns of Uganda’s civil
society stop Bujagali, the most likely alternatives appear to be the
Karuma dam or other hydropower projects. In the discussions which the
World Bank held with Uganda’s Government, the next project in Uganda’s
power sector was always seen to be a hydropower dam, even before the Bank
identified Bujagali as a project. (See Bank Management Response to the
Request for Inspection Panel Review, 13 September 2001, p. 6f.) Thermal
power plants play no role in the debate about the future of Uganda’s power
sector, and the baseline scenario presented by AES’ Project Proposal is
totally unrealistic.
4. Conclusion
The cumulative impacts of the Owen Falls, Owen Falls
Extension and Bujagali dam projects have not been assessed. The problems
of resettlement and rehabilitation have not been resolved. The economic
analysis of the Bujagali project is flawed, and if built, the dam risks
turning into a white elephant project. Essential project documents have
never been released, and so a meaningful public debate and consultation
have so far not been possible. The corruption allegations are still being
investigated.
The Bujagali project has been in the pipeline since
1994. AES has contractually committed itself to developing the project. If
the project is stopped because of concerns about the social, environmental
and economic impacts or about corruption, the most economic alternative
appears to be geothermal power plants, and the politically most realistic
alternative, other hydropower dams on the Nile. The baseline scenario
presented by AES’ Project Proposal is totally unrealistic.
If Price Waterhouse Coopers approves carbon credits for
the Bujagali dam, it will open the door for Dutch government resources to
help fund a dam which has negative environmental , social and economic
impacts and undermines Holland’s commitment to good governance principles.
Furthermore, the Dutch Government, previously seen as a progressive player
in the Climate Change debate, would undermine the Kyoto Protocol as a
whole by meeting its emissions reduction commitments through an
unsustainable and non–additional project.
Peter Bosshard
International Rivers
August 19, 2002
Annex:
NGO letter to AES on Bujagali resettlement problems
Mr. Henry Kikoyo
Project Manager & Company Secretary
AES Nile Power Ltd.
P.O. Box 24401
Kampala, Uganda
July 29, 2002
Resettlement problems of the Bujagali project
Dear Mr. Kikoyo,
On July 14, 2002, we had the chance to visit the
Bujagali project resettlement site at Naminya, and to discuss the
resettlement situation with a group of resettlers, including village
elders. The issues which emerged strongly contradict the claims that "when
it comes to resettlement, Bujagali is a model project", as you had
asserted in a meeting with us on July 11. On the contrary, it appears that
many of the well–known problems of dam–induced involuntary resettlement –
including a lack of adequate compensation, poor quality and insufficient
replacement cropland, lack of adequate common land, fuelwood and water,
culturally inappropriate housing – are being replicated by AESNP at
Bujagali. The resettlers told us that they now had to "sleep with empty
stomachs". Their condition will likely deteriorate once their compensation
funds have been spent.
We tried to contact you after we returned to Kampala
from the Jinja area. We were told that you were on leave but would respond
to our concerns in writing. Below are the main issues which arose from our
visit to Naminya.
Compensation:
- All resettlers we spoke to stated that their crops
and trees had been under–compensated by AESNP.
- One village elder complained that of the USh 700,000
which he received in compensation for lost assets, USh 200,000 were
immediately deducted for transporting his family’s belongings over a
distance of a few kilometers to the resettlement site.
- The resettlers stated that AESNP had contracted them
to clear the land at the resettlement site but that six weeks later they
had still not been paid.
Land and common resources:
- The land at the hilltop resettlement site is stony
and much less fertile than the resettlers’ expropriated riverside plots.
The elders also maintained that the resettlement site received less rain
than their original lands on the banks of the Nile. Some resettlers
complained that the one acre of replacement land they had received was
less than they had previously farmed. We also heard from many men who
had previously tilled two plots of land but had received replacement
land for only one plot. Women complained to us that they had previously
had their own plots but these had not been recognized by AESNP. This
meant that a family comprising of two wives and a husband which
previously had access to three different parcels of land now has to
share a single one–acre plot.
- In spite of promises made by AESNP, the resettlers
said that they have not received legal titles to their new land.
- In a shocking letter dated May 14, 2002, AESNP warned
the oustees not to cultivate their plots since they are still in the
possession of AESNP. The resettlers we spoke to understood the letter to
refer to the new plots for which they have not received titles. The
annex contains a full transcript of the AESNP letter. Not surprisingly
the resettlers were very worried about the potentially disastrous
implications for their livelihoods of AESNP preventing them from growing
crops.
- No grazing land was made available to the resettlers
who own cattle, and they are denied access to nearby common land which
has signs posted declaring any use of the land to be illegal.
- People used to catch fish in the Nile, but they have
been moved away from the river and the place where they used to fish is
fenced off. One ex–fisherman stated that "if we went there now we would
come back with whip marks on our backs". They do not seem to have been
compensated for the loss of this source of food or income. They claimed
that AESNP had promised them a fishpond but had not provided this.
- The resettlers also complained of a serious lack of
firewood at the resettlement site and said that they now had to walk
several kilometers to collect wood.
Water:
- Only one borehole exists for drinking water, which is
several kilometers from some of the houses. Again the resettlers claimed
that AESNP had promised to drill several boreholes, but had failed to do
so. They complained that the water was orange. A rainwater tank has been
erected for each house but resettlers told us that these were too small
and that after only four months, some were already leaking.
Housing:
- The new houses have been built without kitchens or
any other place for cooking. The women of the resettlement site were
extremely angry about having to cook in the open without any protection
from the rain.
- The toilets overflow when it rains, and the
resettlers fear an outbreak of cholera.
- Polygamous families received the standard one–bedroom
house, yet traditionally they would have a separate house (and kitchen)
for each wife and her children. Forcing these families to live in a
single small house was clearly causing distress.
Amenities:
- Unlike where people used to live, there are no
markets, stores or main roads in the vicinity of the resettlement site.
Graves:
- The elders say that they were promised financial
support by AESNP to relocate the graves of their ancestors, but have so
far not received this, and so have not been able to move the graves.
As a consequence of all these problems, the mood at the
resettlement site was extremely grim. It turned into open hostility when
the resettlers for a moment thought that we represented AESNP. People told
us they would "return running" if they could go back to their previous
homes, and some women told us they were considering divorcing their
husbands so that they could return to their original villages. The
resettlers were unanimous in claiming that they were better off before
moving.
The conditions we found at the Naminya site contrast
markedly with the claims in AESNP’s publicity materials. They are all the
more incomprehensible since so far, only about 30 families have been
resettled.
We appreciated your interest to discuss the Bujagali
project with us in Kampala on July 11. We regret that no member of AESNP’s
management was available to register the above concerns, and discuss them
in person, on July 15 or 16.
We urge you to address these serious problems of
compensation, livelihood, land security, housing, amenities, and
compensation for the relocation of graves at the earliest, and to the full
satisfaction of the affected people. We look forward to your response.
We are sending copies of this letter to the Ugandan
Government officials and Members of Parliament we met in Kampala, to
representatives of the World Bank Group, and to the Panel of Experts.
Sincerely yours,
Alfred Belinda
National Association of Professional Environmentalists, Uganda
Peter Bosshard
International Rivers, USA
Christine Eberlein
Berne Declaration, Switzerland
Liane Greeff
Environmental Monitoring Group, South Africa
Patrick McCully
International Rivers, USA
Frank Muramuzi
National Association of Professional Environmentalists, Uganda
Hon. Dr. Ruhakana Rugunda, Minister of Water, Lands, and
Environment
Hon. Daudi Migereko, Minister of State for Energy
Mr. Haran Sivam, Mr. Ronald Anderson and Mr. Eric
Brusberg, International Finance Corporation
Ms. Karen Rasmussen, International Development
Association
Ms. Meg Taylor, Compliance Advisor/Ombudsman
Mr. Edward S. Ayensu, World Bank Inspection Panel
Dr. Lee Talbot, Panel of Experts
Annex:
Letter of AESNP of May 14, 2002
AES Nile Power
Date: 14/5/2002
Name: Khauka Florence, Khauka Goerge [sic], Ella Yakobo,
Wenene Margaret, Waiswa Ezephan, Madekere Paul, Anyorit Benaleta Akong,
Masiga Francis, Gabeya Miria Muzira, Omudu Sunday, Kizza Lawrence, Kirya
Yoronimu
The Chairperson LC1,
Village: Namilyango
Dear Sir/Madam,
RE: TRESSPASS ON THE LAND
We have learnt that the mentioned above are in the
process of cultivating our land at Namilyango village without our
permission. This is to inform you that cultivating our land without our
written permission is criminal and should therefore be stopped immediately
failing which we shall have no alternative but to refer the matter to
police and cause your arrest.
STAND DULY WARNED!
By a copy of this letter the area LC1 authorities are
notified of this warning.
Yours sincerely,
Terry Nantongo
Manager – Legal Services
CC Concerned Trespassers