International Rivers' February 2008 Nam Theun 2 report, based on a recent site visit by International Rivers’ staff, shows that shortcomings and delays in programs to compensate villagers and restore their incomes have not been addressed. Furthermore, it is unclear if resettlement infrastructure for more than 6,200 villagers on the Nakai Plateau will be completed on time for reservoir filling to begin in June 2008.
Contact us: 

Shannon Lawrence
shannon [at] internationalrivers [dot] org
+1-202-664-4616

Download fileSize
Nam Theun 2 Trip Report and Project Update, Feb081.14 MB
NT2 Questions and NTPC Responses61.29 KB