learn more about:Join us! |
Geological Phenomena Cost EEPCo 400 Million BirrApril 22, 2008 Originally published in Walta Information Center The two billion birr Tekeze hydro electric power project, faced with a geological phenomena, has incurred the Ethiopia Electric Power Corporation (EEPCo) another 400 million birr.Mihiret Debebe, general manager of the Ethiopian Electric Power Corporation (EEPCo), told Capital that the obstacle faced at the site would cost the corporation about 15% of the total project cost. He said that, despite the huge problem that could be considered as building another dam, the project is expected to be completed before the rainy season that ends in September.
EEPCo signed the contract at the Hilton Hotel on June 7, 2002, with the Chinese National Water Resources and Hydropower Engineering Corporation (CWHEC) for the construction of the dam that is expected to generate 300MW. Mountains at site leveled down and caused the additional cost for constructing a restraining wall to avoid the shearing of the mountains around the dam. Arch dams are concrete or masonry structures that curve upstream into a reservoir, stretching from one wall of a river canyon to the other. Such dams require a relatively narrow river canyon with solid rock walls capable of withstanding a significant amount of horizontal thrust. The manager said that the problem was not shown on the feasibility study and would have an impact on the completion date of the dam. He further said that the construction work is done 24 hours a day to complete the project on time to commission the power plant before this Ethiopian year.
When completed, Tekeze is expected to add 300MW power to the national grid, putting generating capacity to a total of 1,170MW.
EEPCo plans to construct 10 hydro power plants worth over 13.1 billion dollars, in the next 10 years.
|